June 2025 Update
At the June meeting, Newkirk Novak project managers, reviewed construction progress of our 2025 Bond Issue projects.
- Pathfinder Playground: New concrete sidewalks and a patio with a seating wall has been installed. Grading for the hard surface play area is also complete. The project is scheduled to open for students in the fall of 2025.
- Platte Purchase Site Amenities: Structural masonry walls are being installed, and mechanical and electrical rough-in is ongoing for the concessions and restroom areas. Roof framing will begin next month.
- PCHS Phase 2 and PCHS Track: Crews have begun deconstruction of the southern end of PCHS and will continue throughout July. Soil stabilization and fine grading has been completed for the new PCHS track in preparation for the concrete curbs and asphalt, followed by paving in late June.
May 2025 Update
At the May meeting, Dr. Devin Doll shared our preliminary project timeline as well as the following updates:
- Pathfinder Playground: Members of the Student Lighthouse Team ceremoniously broke ground on the project on May 2. Construction will begin once school ends.
- Platte Purchase Site Amenities: The building pad has been installed and footings have been poured. Mechanical, electrical, and plumbing work will soon begin on site.
- PCHS Phase 2: Paxton is being renovated to house our band, vocal, and theatre programs during PCHS Phase 2 construction. Job site trailers have been placed, and preparations are being made for the deconstruction of the southern end of PCHS which will begin in early June.